Narender Kumar and Others v. Special Land Acquisition Officer-cum-Competent Authority and Others
Arbitration and Conciliation Act, 1996 – Section 29-A(4)
Case brief
What is this about?
Extension of time under Section 29-A(4), Arbitration and Conciliation Act, 1996; arbitrator under Section 3(G), National Highways Act, 1956; National Highways Authority of India-cum-Divisional Commissioner, Mandi; land acquisition in District Kullu, H.P. for National Highway; Arbitration Reference Case No.29 of 2024 (Narender Kumar & others v. Special Land Acquisition Officer); proceedings closed after expiry of statutory period; direction to pass award by 4th December, 2026; last and final opportunity; Himachal Pradesh High Court, Shimla; Arb. Case No.118 of 2026; decided 04.06.2026; Justice Romesh Verma.
What did the court decide?
Extension of time: the Arbitrator (NHAI-cum-Divisional Commissioner, Mandi) directed to conclude the arbitral proceedings and pass the arbitral award in Arbitration Reference Case No.29 of 2024 on or before 4th December, 2026, as a matter of indulgence being the last and final opportunity.