Dinesh Sharma v. UOI and Others
Extension of time – Section 29(4), Arbitration and Conciliation Act, 1996
Case brief
What is this about?
Himachal Pradesh High Court, Shimla (Romesh Verma, J., oral), decided 19.05.2026 — Arbitration Case No. 108 of 2026, Dinesh Sharma v. Union of India & Ors. — petition under Section 29(4) of the Arbitration and Conciliation Act, 1996 seeking extension of time for completion of arbitration proceedings in Arbitration Reference Case No. 355 of 2022 pending before the Divisional Commissioner, Kangra (Arbitrator under Section 3, National Highways Act, 1956); land-acquisition compensation dispute; proceedings found in violation of statutory time schedule; award directed to be passed by 19.11.2026; no precedent cases cited; no monetary quantum involved.
What did the court decide?
Extension of time: the Arbitrator-cum-Divisional Commissioner, Kangra at Dharamshala directed to conclude the arbitral proceedings and pass the arbitral award in Arbitration Reference Case No. 355 of 2022 on or before 19th November, 2026; petition disposed of in these terms.