CWP 3824/2021; Jiwan Lal Sharma v. State of Himachal Pradesh; HHC 2025:HHC:15437-DB; sewerage pipe line; sewer connection; laying of sewer line; obstruction by private respondents; real brothers; ancestral house; Annexure P-1; consensual disposal; inspection by respondent No.4; backside route; three-month timeline; 02.06.2025 appearance; Himachal Pradesh High Court Shimla; Justice Ajay Mohan Goel; Tek Chand Sharma; Rajpal Thakur AAG; Lovneesh Singh Kanwar Senior Advocate; Devender K. Sharma.
What did the court decide?
Consensual direction: petitioner and private respondents to appear before respondent No.4 on 02.06.2025 at 11:00 am for inspection of the area; sewerage pipe line to be laid from the backside of the ancestral house as agreeable to all parties, completion preferably within three months; pending miscellaneous application(s), if any, also disposed of.