NTPC Limited v. State of Hp and Ors.
Land Acquisition Act, 1894 – Section 28-A – Re-determination of compensation – Limitation
Case brief
What is this about?
NTPC Limited v. State of Himachal Pradesh, 27 CWPs decided 19.06.2025 (H.P. High Court, Ajay Mohan Goel, J.) — challenge to Land Acquisition Collector's order dated 28.12.2017 allowing Section 28-A re-determination applications (Koldam Hydro Power Project, Village Panjolth, District Mandi) filed on 16.07.2014 beyond the three-month limitation of Section 28-A and without certified copies of the enhancement award dated 22.03.2014 fixing Rs.5,00,000/- per bigha. Held: Section 28-A limitation is sacrosanct and computed individually per applicant; no condonation; Collector lacked jurisdiction over time-barred applications; orders dated 28.12.2017 quashed as nullities; Section 28-A(3) unavailable to the acquiring company as beneficiary; objection of delay in filing the writ petitions rejected as the petitioners bona fidely pursued the Section 28-A(3) remedy until 2023; Popat Bahiru Govardhane, (2013) 10 SCC 765 relied upon; Shahid, AIR 1997 Kerala 216 and Sant Ram, CWP No. 2207 of 2017 (decided 28.05.2019) distinguished. Petitions partly allowed.