Case brief
What is this about?
Narain Dass Naik v. State of H.P. and another; Arb. Case No.122 of 2025; High Court of Himachal Pradesh, Shimla; decided 16 May 2025; Jyotsna Rewal Dua, Judge; Section 29-A Arbitration & Conciliation Act 1996; extension of time for completion of arbitral proceedings; extension of mandate of Arbitral Tribunal; six months w.e.f. 20.12.2024; final award; claimant completed submissions; petition disposed.
What did the court decide?
Extension of the period for completion of arbitral proceedings, including passing of the final award, by six months w.e.f. 20.12.2024; pending miscellaneous application(s), if any, also disposed of. ¶17