Hareshbhai Laljibhai Nashit v. Dakshin Gujarat Vij Company Limited
Case brief
What is this about?
The High Court entertained an oral order regarding the restoration of an electricity connection. While the appellant argued for depositing a portion of dues in 24 equal monthly installments, the court deemed 18 months sufficient. The appellant must deposit Rs. 10 Lakhs to restore the connection immediately and pay the balance in 18 equal monthly installments.
What did the court decide?
The appellant to deposit Rs.10 Lakhs for immediate restoration of connection and pay the remaining balance in 18 equal monthly installments.