Deepak Bora v. the State of Assam and Othrs
Case brief
What is this about?
Gauhati High Court writ petition dismissed; PWD road contract cancellation notices/orders dated 03.11.2025 and 11.11.2025; completion period 12 (twelve) months from 20.06.2023; only 28% work completed per Respondents; no case on merits for judicial review; extension of 6 (six) months and non-re-tendering refused; no costs; Judge Devashis Baruah; date 13.05.2026.
What did the court decide?
Upon perusal of the materials on record and the orders passed by the Respondent Authorities, this Court held that the Petitioner failed to make out any case on merits for the Court to exercise its powers of judicial review. ¶¶22