Sushil Agarwal v. the State of Assam and 4 Ors.
Case brief
What is this about?
Illegal/unauthorised construction beyond permissible limits; building bye-law violation; demolition notice dated 16.11.2021 and reminder dated 26.11.2021; failure of Tinsukia Municipal Board and Executive Magistrate to act on complaints; boundary demarcation by District Commissioner, Tinsukia before demolition; earlier Circle Officer demarcation opposed by petitioner; Article 226 mandamus; disposal with directions instead of adjudication; six-week compliance timeline; consent to demolition and waiver of compensation claim; respondent Ranjan Sovasaria.
What did the court decide?
District Commissioner, Tinsukia directed to demarcate the boundary between the petitioner and respondent No.5 and thereafter demolish the illegal construction work of respondent No.5 noted in the demolition notices dated 16.11.2021 and 26.11.2021, with due care and caution, within six weeks; certified copy to be placed before respondent Nos.2, 3 and 4 within one week.