Navajyoti Sarma v. Union of India and 9 Ors.
Case brief
What is this about?
Maa Kamakhya Temple Access Corridor; PIL/12/2024; WP(C) 2700/2024; Gauhati High Court; Ashutosh Kumar CJ; Arun Dev Choudhury; Nilachal Hill; Dasa Mahavidyas; PM-DEVINE Scheme; PRASHAD Scheme; Ancient Monuments and Archaeological Sites and Remains Act 1958; Assam Ancient Monuments and Records Act 1959; NIT dated 27.11.2023 tender; IIT Guwahati hydrological geophysical study; National Institute of Hydrology Roorkee; MOU PWD Building Assam; underground holy water springs; protected prohibited relocated areas; no-construction undertaking withdrawn; liberty to revive petition on breach; two-page affidavit; White Paper prayer; sacrilege/desecration concern; Larsen and Toubro concessionaire.
What did the court decide?
Both petitions (PIL No. 12/2024 and WP(C) No. 2700/2024) closed and disposed of; State permitted to proceed with construction/execution of the Maa Kamakhya Temple Access Corridor project subject to reiterated assurances (execution per drawings/designs approved by IIT Guwahati, without affecting the temples or the underground holy water springs); liberty reserved to petitioners to revive the petitions upon any breach noticed till final execution of the works, by filing a two-page affidavit.