Gauhati High Court WP(C)/1217/2026 decided 06.03.2026 by Manish Choudhury, J. (2026:GAU-AS:3367); NHIDCL EPC contract suspension; Clause 22 Contract Agreement allotment without notice; NH-37A Kaliabor-Tiniali to Kolong Bridge Nagaon service road RCC drain; 97.5% progress, balance 2.5%; Rs. 7,50,000/- vs Rs. 39,53,182/-; R4 M/s Risha Infrastructure; undertaking to complete by 27.03.2026; suspension kept in abeyance/revival on default; writ petition disposed of on undertaking; no costs; Union of India; Sanjay Kumar Singh Tinsukia.
What did the court decide?
Petitioner directed to act in accordance with his undertaking; respondent NHIDCL authorities to allow him to execute the remaining 2.5% part of the Contract-Work at the agreed Contract Value on or before 27.03.2026 (suspension order kept in abeyance for that period per recorded submissions); upon failure, NHIDCL at liberty to take further action in terms of the Contract Agreement and recorded submissions (including through respondent no. 4) without further reference to the Court; earlier interim order merged with this order; no order as to costs.