Rajendra Choudhury v. the District Commissioner and 4 Ors.
Case brief
What is this about?
Contractor sought refund of Rs. 4 lakh deposited as advance forest royalty for permits to carry boulders for an allotted road-protection work. Respondents did not dispute the claim. Court directed authorities to verify the claim and refund the amount with applicable taxes and charges within three months.
What did the court decide?
Direction to respondents to verify the claim and refund Rs. 4,00,000 with applicable taxes and charges within three months if entitlement is established.