M/S Drishti Enterprise and Anr. v. the State of Assam and 10 Ors.
Case brief
What is this about?
Opportunity-of-hearing case: Gauhati High Court set aside departmental order dated 08.10.2021 fixing the contractor's admissible bill at Rs. 4,88,802/- (plus security deposit Rs. 1,17,635/-) because the valuation meeting of 18.09.2021 was held in the contractor's absence, only a post-decisional hearing was afforded (held insufficient for effective hearing), and the order ignored the Executive Engineer's work completion certificate and Salvage report despite the earlier direction in WP(C) 219/2020 (disposed 11.08.2021). Fresh decision directed with the petitioner's participation, assistance of EE PWD Guwahati Electrical Division, and transparent calculation of claims/counter-claims; 60-day decision timeline, further 60 days for payment; no costs. Parties: Drishti Enterprise / Dhrubajyoti Bhagawati v. State of Assam, Sports Authority of Assam, PWD (Building/Electrical) officials. Case: WP(C)/554/2022, decided 02.12.2025, single Judge (Rajesh Mazumdar). Amounts appearing: Rs. 40,43,944; Rs. 23,52,696; Rs. 16,91,248; Rs. 28,41,498; Rs. 4,88,802; Rs. 1,17,635; Rs. 5,460. Subject: PWD electrical/high-mast sports lighting works, FIFA U-17 World Cup 2017, S.S. Stadium Sarusajai, Guwahati.