Vermibed with Shade. In the said item, the Respondent No.4 became L6 and the Petitioner was L5 bidder. It was also mentioned that going by the normal practice, the L1 bidder gets the work order and the Respondent No.4 who is the L6 bidder will get work order only if other bidders above him including the Petitioner is not able to fulfill the work order for some reason or the other. It was further mentioned that the Respondent No.4 had submitted the turnover certificate for 2019-2020 to 2021-22. However, as per Clause 4.2.2 of the NIT document as reflected in the Corrigendum, turnover for the year 2020-21 to 2024-25 was required to be submitted. The matter was discussed in the Departmental Bid Committee’s Meeting held on 27.09.2025 and it was decided that as the turnover certificate is a historical document as per Clause 23.15(ii) of the Assam Public Procurement Rules, 2020, therefore the Respondent No.4 should be communicated for submission of the turnover certificate for the rest of the period. It was also mentioned that pursuant thereto, on being complied, the firm was considered technically responsive. In addition to that, it was also mentioned that Form B9 is a checklist of the documents to be submitted and non-submission of the Form B9 cannot be a ground for rejection of the bid.