M/S Naduar Koibarta Mach Mara S. S. Ltd. v. the State of Assam and 4 Ors.
Case brief
What is this about?
Gauhati High Court; WP(C)/4940/2023; decided 12.06.2025 by Justice Michael Zothankhuma; fishery settlement dispute; embankment constructed by Forest Department; removal/demolition of embankment separating Saru dolapani and Bor Dolapani beel; compliance report dated 10.06.2025 by Circle Officer, Naduar Revenue Circle, Sootea; letter dated 10.06.2025 by District Commissioner, Biswanath; bamboo fencing erected 11.06.2025 and ordered demolished; Tewaripal Eco Development Committee (registered under Rule 7 VII of the Assam Joint Peoples Participation Forestry Management Rules 1998) as respondent No. 8; Divisional Forest Officer, Western Range, Nagshankar; writ petition closed as infructuous; documents marked Annexure-X; appearance of Deputy Commissioners Sonitpur and Biswanath dispensed with.
What did the court decide?
No substantive relief adjudicated; writ petition closed as infructuous after the embankment's removal was reported and the Deputy Commissioner, Biswanath undertook demolition of the subsequently erected bamboo fencing; personal appearances of the Deputy Commissioners, Sonitpur and Biswanath dispensed with.