Salman Hind v. the State of Assam and 4 Ors.
Case brief
What is this about?
Contractual dues; unpaid contractor; Water Resources Department Assam; Hailakandi Water Resources Division; work order verification; work completion certificate; work completion report; Measurement Book; affidavit-in-opposition; disputed question of fact; civil court remedy; writ petition disposed with direction; 4 months timeline; Dhaleswari/Dhaleswar river; Katakhal river; Dhilaidhar dyke; Tasla Dam drainage basin; CM Special Package; WP(C)/430/2025; Gauhati High Court; Michael Zothankhuma J.
What did the court decide?
Direction to respondent nos. 2 and 4 to verify, within 4 months of receipt of a certified copy of the order, whether the work orders listed in paragraph-6 of the affidavit-in-opposition were completed by the petitioner and, if completed, to pay the outstanding amounts; liberty to pursue claims for works with no traceable work orders before the Civil Court.