Krishna Kanta Biswas v. the State of Assam and 4 Ors.
Case brief
What is this about?
WP(C)/3710/2024, Gauhati High Court, order dated 07-03-2025, Kardak Ete, J.; Krishna Kanta Biswas v. State of Assam & 4 Ors; Irrigation Department; contractor's bill payment; Solar powered MDTW scheme Guimari and Dakhinpat; SOPD 2017-18; Nagaon Division (Irrigation); Rs.7,35,237/-; claim admitted/undisputed; Chief Engineer Chandmari directed to verify within two months and pay within three months; writ petition disposed.
What did the court decide?
Direction to respondent No.2, the Chief Engineer, Minor Irrigation, Chandmari, to verify the petitioner's claim of Rs.7,35,237/- within two months and, if found admitted, to pay the same to the petitioner within three months thereafter. ¶30