Smti Rupali Bordoloi v. the Assam Power Distribution Company Ltd. and 4 Ors.
Case brief
What is this about?
WP(C)/1354/2016, Gauhati High Court, decided 07.01.2025 by Michael Zothankhuma, J. Petitioner Smti Rupali Bordoloi versus APDCL/UAEDCL/ASEB officials. Unpaid, time-barred contractual dues of deceased contractor Bipin Chandra Bordoloi for works executed 1996-1998 under Teok Electrical Division; follows Abdul Kasem Ali Ahmed vs. State of Assam & Others, 2007 (1) GauLT 784. Direction to pay Rs.1,55,152.50 within 10 weeks; petition disposed of.
What did the court decide?
Respondents directed to pay the petitioner Rs.1,55,152.50, the admitted unpaid contractual dues of her late husband, within 10 (ten) weeks from the date of receipt of a certified copy of the order; the letter dated 04.01.2025 and the enclosed Statement taken on record and marked Annexure-X collectively. ¶46