Minarul Amin v. the State of Assam and 5 Ors.
Case brief
What is this about?
A contractor sought release of Rs.1,00,170/- in contractual bills for flood damage restoration works on an embankment, backed by a Completion Certificate from the Executive Engineer. With the respondents' parawise comments not denying the claim, the court directed release of funds and payment within four months.
What did the court decide?
Payment of admitted contractual dues of Rs.1,00,170/- within 4 months; respondent no.5 to make funds available.