Power Grid Corporation of India Ltd. v. Dr Lalsiampara and 9 Ors.
Case brief
What is this about?
The High Court dismissed an application seeking condonation of a 700-day delay in filing a connected civil revision. The court held that the applicant failed to establish due diligence and good faith required under Section 14 of the Limitation Act, 1963, noting unexplained gaps and a 75-day interval between withdrawn writ petitions.
What did the court decide?
Application for condonation of delay in filing civil revision dismissed.