S R Engineering Construction v. the Commander Works Engineer
Case brief
What is this about?
Petitioner sought appointment of a sole arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 arising from a power house construction contract. Court, noting respondent's lack of objection, appointed a surveyor as arbitrator while preserving respondents' right to challenge maintainability.
What did the court decide?
Appointment of Sri (Er.) Jadav Goswami, Surveyor, Valuer, Loss Assessor as sole arbitrator.