What is this about?
The petitioner, a supply contractor, challenged the State's failure to honor a bill for supplied flower pots and saplings. The High Court held that lack of technical sanction and late verification were not valid denials. The Court directed the Principal Chief Conservator to conduct a hearing and pass orders for payment within two months if supplies were verified. The Writ Petition was finally disp
What did the court decide?
The petitioner was directed to apply to the Principal Chief Conservator for a hearing to establish supplies made, and he was directed to pass payment orders within two months if established.