The Court directed the Chief Engineer (Water Resources) to take up with authorities for release of funds for two completed schemes. The petitioner is entitled to Rs. 59,74,779/-, which is withheld due to non-receipt of state share funds. The Court ordered payment as and when funds are received.
What did the court decide?
Direction to Respondent No. 2 to take up the matter with concerned authorities for release of funds pursuant to specific Head of Account so that the amount due is paid to the petitioner as and when re