Pcm Cement Concrete Pvt. Ltd. v. Union of India and 2 Ors.
Case brief
What is this about?
The High Court allowed the appeal and remanded the Section 9 injunction petition to the Additional District Judge. It held that the judge erred by not examining whether the mandatory notice under the contract was issued before deducting disputed maintenance costs, a question that should have been decided prima facie.
What did the court decide?
The order dated 09.01.2019 is set aside and the matter remanded to the learned Additional District Judge No.2, Kamrup (M).