The petitioner is a registered contractor under PWD (Roads), Government of Assam. As against the Notice Inviting Tender No. CEM/14/Pt/2013/26 dated 03.02.2016 issued by the office of the Chief Engineer, PWD (Roads), Assam for lifting of scrap materials under PWD (Roads), Barpeta State Road Division and under PWD (Roads), Nalbari Rural Road Division. It is the contention of the petitioner that the competent authority accepted the bid of the petitioner and work orders were issued to the petitioner. In compliance thereof, the petitioner deposited the requisite bid value amounting Rs. 4,17,912/- for works under PWD (Roads), Barpeta State Road Division and an amount of Rs. 11,34,672/- for the works under the Nalbari Rural Road Division on 04.04.2017. When the petitioner went to the offices of the respondents No. 4 and 5 for the purpose of making payment of VAT, the said respondents No. 4 and 5 declined to issue the requisite challan for deposit of the VAT on the ground that the work orders issued to the petitioner were stayed by the Chief Engineer. Later on, he received the letters of cancellation of the work orders from the Chief Engineer, PWD (Roads) dated 08.03.2017. It is submitted that the petitioner were issued work orders and without giving any opportunity of being heard, cancelled the work orders so issued to him which is illegal. The Chief Engineer, PWD (Roads), the respondent No. 2 by way of the additional affidavit-in-opposition put on record that in the said NIT there were 11 participants for auction of old and serviceable materials under the aforesaid two divisions. Out of the said 11 participants, 4 participants were qualified as the successful bidders. The petitioner was disqualified due to deposit of less earnest money. The highest bidder expressed its inability to lift the materials whereafter the petitioner was issued the work order/ allotment order inadvertently by the then Chief Engineer, PWD (Roads) who retired on 28.02.2017.