What is this about?
This is an original recovery application allowed by the Debts Recovery Tribunal. The Tribunal rejected the defendants' objections regarding blank documents and varied the interest rate from contractual to 13.25% p.a. permitting recovery from sale of mortgaged property.
What did the court decide?
Defendants directed to pay Rs.73,21,414/- with interest @13.25% p.a. and costs; recovery via sale of mortgaged property granted.