M Praveen Kumar v. City Union Bank Limited
Case brief
What is this about?
The Debt Recovery Tribunal, Chennai, dismissed a maintenance application seeking to condone a 129-day delay in filing a Securitization Application under the SARFAESI Act. Relying on Supreme Court precedents, the Tribunal held that Section 17 is mandatory, the 45-day limit is statutory and cannot be condoned on equitable grounds, and the applicant failed to explain the delay.
What did the court decide?
The present Maintenance Application No. 142 of 2025 stood dismissed. Consequently, Securitization Application No. 217 of 2025 also stood dismissed. Any interim order granted was vacated.