Bank of Maharashtra v. Mr. Joe Varghese Padasssari
Case brief
What is this about?
The Recovery Tribunal allowed an original application filed by Bank of Maharashtra for recovery. The defendants were ex-parte. The court held them jointly and severally liable to pay the principal sum with future interest and costs. The claim secured by mortgage is directed to be realized.
What did the court decide?
Defendants to pay Rs. 55,04,809.79 plus future interest at 10.25% p.a.; claim secured by mortgage to be realized; bank entitled to costs and recovery certificate.