The Tribunal allowed a miscellaneous application to issue a recovery certificate after a respondent defaulted on a joint compromise installment. The bank was directed to get a certificate for the original claim plus future interest, less the amount remitted, and future asset sale was directed.
What did the court decide?
Recovery certificate issued for the claimed sum less 6 Lakhs remitted; OA schedule property directed to be sold on failure to pay.