Central Bank of India v. Smt Archana Devi and Others
Case brief
What is this about?
The appellant bank filed an original application for recovery of dues arising from a default in a secured housing loan facility. The tribunal examined the evidence, noted the respondents' absence, and allowed the application. It directed the respondents to pay the principal sum with interest and cost, and issued a recovery certificate.
What did the court decide?
The respondents directed to pay Rs. 36,88,854 along with interest and costs within 30 days; Recovery Certificate to be issued for enforcement.