The Karur Vysya Bank Ltd., v. Mr. Sivakumar. E
Case brief
What is this about?
The Tribunal allowed the bank's application for a Recovery Certificate under the RDB Act. The bank proved the loan disbursement via unchallenged affidavits. While agreeing the claim was valid, the Tribunal modified the interest rate from contractual rate to 8% simple interest pendente lite and approved recovery from assets and personal liability.
What did the court decide?
Recovery Certificate issued to realize Rs.59,01,494.02p with 8% simple interest from filing date; defendant personally liable if assets insufficient.