Punjab and Sind Bank v. Mrs Kiran Vats and Ors.
Case brief
What is this about?
The Debt Recovery Tribunal allowed the bank's application for recovery of dues. Based on the tripartite agreement, the court held the builder liable to refund the entire loan amount paid by the bank to them upon the borrower's default, as the property was never allotted or possession handed over. The application was allowed against the builder as a third party.
What did the court decide?
Directs defendant no. 3 to pay Rs. 20,45,510.90 with costs and interest @ 12.25% p.a. from the date of filing of T.A. or face recovery from property sale.