The Debts Recovery Tribunal allowed the applicant bank's origin exterior application for recovery of dues against the borrowers and guarantors. Based on the default in financial discipline and failure to clear dues after demand notice, the Tribunal imposed a repayment order on the amount claimed, granted simple interest at 12% per annum, and issued a Recovery Certificate against the mortgaged and personal properties.
What did the court decide?
The defendants are ordered to pay Rs. 4,38,78,516.10 jointly and severally along with simple interest @ 12% per annum. Recovery Certificate issued under Section 19(2) of RDB Act. Defendants restrained from alienating assets without payment.