Punjab National Bank v. Bohar Singh and Another
Case brief
What is this about?
The Debts Recovery Tribunal allowed the Bank's application under S.19 RDBFIL Act for recovery of Rs.41.05 lakh outstanding on a KCC loan. The Tribunal decreed payment of principal with simple interest at 8% p.a. and ordered issuance of a Recovery Certificate after defaulting defendants failed to appear ex-parte.
What did the court decide?
Declared defendants liable to pay Rs.41,05,131.00 plus interest at 8% p.a. Issued Recovery Certificate. Order enforceable via sale of mortgaged or personal assets under SARFAESI Act.