Punjab National Bank v. Harvinder Pal Singh Alias Harwinder Pal Singh
Case brief
What is this about?
The Debts Recovery Tribunal allowed the bank's application for recovery of Rs.24.53 lakhs. The court reconsidered the interest rate to 8% p.a. over the claimed 9.75% and ordered a recovery certificate and attachment of properties if dues remain unsatisfied.
What did the court decide?
Defendant to pay Rs.24,53,804.61 with costs and interest @ 8.00% p.a.; Recovery Certificate issued; Authorised sale of mortgaged/personal assets.