Punjab National Bank v. Surjit Singh and Another
Case brief
What is this about?
The Debt Recovery Tribunal allowed the applicant bank's original application for recovery of an outstanding loan amount of Rs. 31,21,854.00 from two respondents, who failed to repay their loan and guarantees. The Tribunal granted uniform simple interest at 8% p.a. and directed issuance of a Recovery Certificate.
What did the court decide?
Recovery ofRs. 31,21,854.00 jointly and severally with simple interest at8% p.a.; Recovery Certificate issued.