Hdfc Bank Ltd., v. G Ravi Kumar
Case brief
What is this about?
The Debts Recovery Tribunal allowed the Applicant Bank's Original Application for recovery of Rs. 21,87,931.13 plus future interest and costs. The Respondent defendant remained ex parte, and the tribunal held the evidence affidavit and documents sufficient to establish liability.
What did the court decide?
Decree for payment of Rs. 21,97,931.13 with future interest and costs; Recovery Certificate to be issued; Authority to realize dues.