Hdfc Bank v. Maroju Chandrashekar
Case brief
What is this about?
In Debt Recovery Tribunal-II Hyderabad, the Presiding Officer allowed an original application filed by HDFC Bank Ltd. for the recovery of a principal sum of Rs. 21,39,204.55 along with future interest and costs against a defendant who appeared ex-parte.
What did the court decide?
Order allowed the Original Application; directed the Defendant to pay Rs. 21,39,204.55 with future interest @ 10.50% p.a., costs, and issued a Recovery Certificate.