Phorum Jigneshbhai Brahmbhatt v. Punjab National Bank
Case brief
What is this about?
The Tribunal disposed of a restoration application (M.A. No. 125/2023) seeking to reinstate an appeal dismissed for default of non-payment of the third instalment of pre-deposit. The court accepted the appellants' explanation of a one-day logistical delay, allowed the restoration, restored the interim order, and directed SARFAESI measures to remain in effect until the next hearing.
What did the court decide?
Application for restoration allowed; appeal restored to file; interim order and SARFAESI measures restored.