M/S. Vnr Enterprises and Ors. v. Union Bank of India
Case brief
What is this about?
The DRTA dismissed the appeal because justice would fail without entertaining it due to the Presiding Officer ignoring the prima facie case. While finding the bank's liability calculation potentially contested, the court reduced the mandatory 50% pre-deposit from ₹ 6.17 crores to ₹ 4 crores considering the appellant's financial strain. A stay was granted upon deposit of ₹ 50 lakhs as the first pre-deposit, stalling SARFAESI measures on properties under the secured application.
What did the court decide?
Stay granted on further SARFAESI measures pending deposit of total pre-deposits of ₹ 4 crores, paid in instalments starting with ₹ 50 lakhs within three weeks.