Excelling Geo and Engineering Consultant Private Limited v. C S Construction Company Private Limited & Anr.
Enforcement/execution of arbitral award – Withdrawal
Case brief
What is this about?
Delhi High Court, OMP (ENF.) (COMM.) 89/2026, order dated 20.04.2026 by Harish Vaidyanathan Shankar, J.; Decree Holder Excelling Geo and Engineering Consultant Private Limited v. Judgement Debtors C S Construction Company Private Limited & ANR.; enforcement and execution of Domestic Award dated 23.03.2026 passed by Sole Arbitrator; Section 36 of the Arbitration and Conciliation Act, 1996 read with Order XXI CPC; accompanying applications under Order 21 Rule 54 and Order 21 Rule 41(1) and (2) read with Section 151 CPC; petition withdrawn as prematurely filed; dismissed as withdrawn with liberty granted.
What did the court decide?
Liberty to withdraw the prematurely filed Petition granted; the Petition along with pending application(s) dismissed as withdrawn. ¶16