M/S Vivaan Solar Pvt. Ltd. v. Northern Railways
Arbitration & Conciliation Act, 1996 – Section 29A – Extension of time for concluding arbitration proceedings
Case brief
What is this about?
O.M.P.(MISC.)(COMM.) 61/2026, High Court of Delhi, Avneesh Jhingan J, 15.01.2026; Vivaan Solar Pvt Ltd v. Northern Railways; Section 29A Arbitration & Conciliation Act 1996; extension of time for concluding arbitration proceedings by four months; no objection by respondent; petition disposed of.
What did the court decide?
Extension of the time period for conclusion of the arbitration proceedings by four months. ¶14