Bucon Engineers and Infrastructure Pvt. Ltd. v. Gail India Ltd.
Case brief
What is this about?
O.M.P.(MISC.)(COMM.) 309/2026, High Court of Delhi, decided 09.04.2026 by Justice Avneesh Jhingan. Petitioner: Bucon Engineers and Infrastructure Pvt Ltd (Counsel: Ms. Madhuri Negi); Respondent: GAIL India Ltd (Counsel: Mr. Nishant Awana, Ms. Rini Badoni, Ms. Nitya Sharma). Section 29A Arbitration & Conciliation Act, 1996 extension of arbitration period granted by six months from 08.02.2026; petition disposed of.
What did the court decide?
Extension of the time period for conclusion of the arbitration proceedings by six months from 08.02.2026. ¶16