Great Eastern Energy Corporation Limited v. Sopan Projects
Arbitration and Conciliation Act, 1996 – Sections 33 and 34 – Amendment of award vis-à-vis challenge
Case brief
What is this about?
Delhi High Court, FAO(OS) (COMM) 101/2023 & 103/2023 (C. Hari Shankar & Om Prakash Shukla, JJ., 15.04.2026), Great Eastern Energy Corporation Limited v. Sopan Projects: scope of Section 34 challenge where award amended under Section 33; challenge lies to amended award, not original award; Single Judge's setting aside of original award dated 25.08.2017 in paras 29-37 of judgment dated 26.04.2023 held without prayer and in excess of jurisdiction; U.S.S. Alliance v. State of U.P. (2023 SCC OnLine SC 778) relied on; paras 29-37 set aside, para 28 upheld; appeal disposed of.
What did the court decide?
Appeal disposed of: impugned judgment upheld only to the extent of para 28 (setting aside the amended arbitral award dated 10 November 2017); observations and findings in paras 29 to 37, including the setting aside of the original arbitral award dated 25 August 2017, set aside; no opinion expressed on other aspects; parties left to their own remedies as available in law.