National Projects Contruction Coproation Ltd. v. Paragon Construction India Pvt. Ld.
Condonation of delay – Section 151, Code of Civil Procedure, 1908
Case brief
What is this about?
Delhi High Court, FAO(OS) 519/2009, National Projects Contruction Coproation Ltd. v. Paragon Construction India Pvt LD., order dated 29.01.2026; CM APPL. 15539/2009 under Section 151 CPC for condonation of 59 days' delay in re-filing rejected for want of sufficient cause; appeal dismissed for want of prosecution; bench Vivek Chaudhary and Renu Bhatnagar, JJ.
What did the court decide?
As no sufficient cause was shown for condoning the 59 days' delay in re-filing (and no one appeared for the appellant when called), the condonation application CM APPL. 15539/2009 is rejected. ¶14