M/S Nkg Infrastructure Ltd. v. Airport Authority of India (Aai) through Djm/Jt. Gm Engg. (C) Jabalpur Airport
Case brief
What is this about?
Section 9 petition alleging violation of an earlier order restraining coercive steps pending arbitration against a compensation demand by AAI. The court found no violation as the impugned letter reflected a fresh quantification, refused relief on the bank guarantee for want of pleading, and directed forthwith constitution of the Dispute Resolution Committee under Clause 25 of the GCC.