Power Grid Corporation of India Ltd. v. Jv of Utkal Galvanizers Limited and Jagabandhu Enterprisers (P) Ltd, through M/S Utkal Galvanizers
Case brief
What is this about?
Power Grid Corporation of India Ltd v. JV of Utkal Galvanizers Ltd and Jagabandhu Enterprisers (P) Ltd; OPTCL (Odisha Power Transmission Corporation Ltd); Arbitration and Conciliation Act 1996 Sections 34 and 36; CPC Order XXIII Rule 1 & 3, Order XXIII Rule 3, Section 151, Order XXI Rule 10 and 11(2); Arbitral Award dated 01.09.2021 by Sole Arbitrator; withdrawal of Section 34 petition; Tripartite Settlement Agreement dated 15.01.2026; settlement amount Rs. 9,00,00,000/- (nine crore); deposit of Rs.15,15,71,761/- refunded with accrued interest; award amount Rs. 6,48,32,312/-; execution petition disposed as infructuous; NOA dated 12.10.2009; Contract Agreements dated 26.11.2009; termination 03.05.2013; Delhi High Court; Subramonium Prasad, J.; order dated 04.02.2026.
What did the court decide?
Permission to withdraw O.M.P. (COMM) 367/2021 effectively granted: petition disposed of under Order XXIII Rule 3 CPC in terms of the Tripartite Settlement Agreement dated 15.01.2026 along with pending application(s); Registry directed to refund the entire deposited amount (Rs.15,15,71,761/-) with accrued interest to enable PGCIL to pay UGL the settlement amount of Rs. 9,00,00,000/-; companion enforcement petition OMP (ENF.) (COMM.) 41/2023 disposed of as infructuous.