Nbcc India Ltd. v. Richa Construction Ltd.
Arbitration and Conciliation Act, 1996 – Sections 28(3), 31(3), 34; Indian Contract Act, 1872 – Section 73
Case brief
What is this about?
Delhi High Court, O.M.P. (COMM) 481/2018 & O.M.P. (COMM) 355/2019, Avneesh Jhingan J, decided 04.05.2026 — Section 34 Arbitration and Conciliation Act 1996 — arbitral award dated 28.06.2018 set aside as against public policy — violation of Section 31(3) (absence of reasoning) on 1.35% rebate and bid amount / 7% deduction for balance of final bill — damages under Section 73 Indian Contract Act 1872 awarded without proof of actual loss (underutilization of labour force, overheads, shuttering & centring) — Unibros v. All India Radio 2023 SCC OnLine SC 1366, Dyna Technologies v. Crompton Greaves (2019) 20 SCC 1, Som Datt Builders v. State of Kerala (2009) 10 SCC 259 relied on — Naval Dockyard Mumbai subcontract — M/s Richa Construction Co. v. NBCC — parties at liberty to avail fresh arbitration.
What did the court decide?
Both petitions under Section 34 allowed; impugned award dated 28.06.2018 set aside; parties at liberty to avail fresh arbitration in accordance with law.