Centium Homes Private Limited v. Satish Kumar Kohli & Ors.
Case brief
What is this about?
Section 37 appeal against Section 17 interim order dated 30.04.2025; collaboration agreement; demolition and reconstruction of plot; contractor's consideration second floor; interim relief amounting to final relief objection; GPA execution clause 11; counter-claim; status quo title and possession second floor; restraint on alienation and encumbrance; consent disposal; appearance before SDM/Sub-Registrar 26.02.2026; Centium Homes Private Limited v Satish Kumar Kohli; Delhi High Court; Avneesh Jhingan; Arbitration and Conciliation Act 1996.
What did the court decide?
Consensual arrangement recorded: directions to the contractor and restrictions on the land owner kept intact; land owner to execute a GPA in terms of clause 11 of the collaboration agreement for the second floor in favour of the contractor, subject to no sale, no encumbrance and no handing over of possession of the second floor to a third party till the outcome of arbitration; parties to appear before the concerned SDM/Sub-Registrar on 26.02.2026 at 11:00 AM and the contractor to hand over possession the same day in compliance with the order dated 30.04.2025; appeal and pending applications disposed of.