M/S Sharma Enterprises v. Hindustan Prefab Limited & Anr.
Case brief
What is this about?
Section 11 Arbitration and Conciliation Act 1996; appointment of Sole Arbitrator; ARB.P.; Delhi High Court; DIAC Delhi International Arbitration Centre; DIAC (Administrative Cost and Arbitrators’ Fees) Rules 2018; Section 12 declaration; Clause 25 arbitration clause; Dispute Resolution Committee DRC decision 15.01.2025 rejecting claims; Project Contract Closure Agreement 04.08.2022; final bill unpaid; interest component; NIHFW National Institute of Health and Family Welfare principal and agent; Hindustan Prefab Limited; Sharma Enterprises proprietorship; Contract Agreement 20.10.2016; fire-fighting and fire detection system upgradation NIHFW Campus Munirka; claim Rs. 1,19,78,900; counter-claims; arbitrability and preliminary objections left open; Mini Pushkarna; Amrit Pal S. Gambhir Sole Arbitrator.
What did the court decide?
Petition disposed of with appointment of Mr. Amrit Pal S. Gambhir, Advocate as Sole Arbitrator; arbitration to be conducted under the aegis and Rules of DIAC, Delhi High Court; remuneration per DIAC (Administrative Cost and Arbitrators’ Fees) Rules, 2018; Section 12 declaration required; counter-claims permitted; all rights and contentions (including arbitrability and the Closure Agreement objection) left open; parties to approach the Arbitrator within two weeks.