M/S Asian Construction Company v. Rites Limited
Arbitration and Conciliation Act, 1996 – Sections 11(6), 16 and 12(2)
Case brief
What is this about?
Delhi High Court, ARB.P. 174/2026, Subramonium Prasad J — Section 11(6) Arbitration and Conciliation Act 1996 — appointment of sole arbitrator — 'when in doubt, refer' — arbitrability and procedural lapse objections left to be raised before Arbitrator under Section 16 — arbitration under DIAC aegis — construction contract, Pondicherry University Convention Centre — Asian Construction Company v RITES Limited.
What did the court decide?
Petition disposed of with appointment of Mr. Nand Lal Singh, Retd. Engineer, as Sole Arbitrator to adjudicate the disputes; arbitration under the aegis of DIAC; disclosure under Section 12(2) within two weeks; all rights and contentions of the parties kept open. ¶¶25